PRINCE2 (Projects IN Controlled Environments) is a widely recognized project management methodology used by organizations around the world. PRINCE2 Foundation is one of the levels of certification offered by PRINCE2, designed to equip individuals with the foundational knowledge and skills needed to effectively manage projects using the PRINCE2 methodology. The PRINCE2-Foundation exam is a written exam that tests the candidate's understanding of the PRINCE2 methodology and principles.
How much PR2F Exam Cost
The price of the PR2F exam is $176 USD.
NEW QUESTION # 62
What process aims to ensure accurate progress information is provided to the Project Manager?
- A. Starting up a Project
- B. Directing a Project
- C. Managing Product Delivery
- D. Managing a Stage Boundary
Answer: C
NEW QUESTION # 63
Which is a type of issue?
- A. A scope tolerance
- B. An expected dis-benefit
- C. An off-specification
- D. A project outcome
Answer: C
NEW QUESTION # 64
Which is created during the Starting up a Project process?
- A. Project management team role descriptions
- B. Project mandate
- C. Communication Management Strategy
- D. Quality Register
Answer: A
NEW QUESTION # 65
Which is a purpose of a quality register?
- A. To record the quality management approach for a product
- B. To issue a unique reference number for each product
- C. To identify corrective actions that are required after an audit by quality assurance
- D. To detail the number and type of quality activities to be conducted
Answer: D
Explanation:
Reference http://prince2.wiki/Quality#The_Quality_Register
NEW QUESTION # 66
What should be recorded in a quality register?
1. Activities to ensure the products are fit for purpose
2. Identified threats and opportunities
3. Problems and concerns to be managed informally
4. Roles responsible for reviewing the project's products
- A. 3 and 4
- B. 1 and 4
- C. 1 and 2
- D. 2 and 3
Answer: B
NEW QUESTION # 67
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
- A. Those who will specify the desired outputs of the project
- B. Those who will create the project's outputs
- C. Those who will manage the project on a day-to-day basis
- D. Those with a financial interest in the project
Answer: D
Explanation:
PRINCE2 identifies three primary categories of stakeholders: 1) those who will specify the desired outputs (customers/users), 2) those who will manage the project on a day-to-day basis (suppliers), and 3) those who use the project's outputs. Those with a financial interest in the project are not explicitly categorized as one of the primary stakeholder types in PRINCE2. References: PRINCE2 Foundation official study guide and materials.
NEW QUESTION # 68
Identify the missing word in the following sentence relating to one of the principles:
A PRINCE2 project should have [?] defined for each project objective.
- A. themes
- B. tolerances
- C. processes
- D. principles
Answer: B
Explanation:
Section: Volume B
NEW QUESTION # 69
Which process is triggered towards the end of the final stage when all the assigned work has been completed?
- A. Closing a Project
- B. Managing a Stage Boundary
- C. Controlling a Stage
- D. Managing Product Delivery
Answer: A
NEW QUESTION # 70
Which is an objective of the 'managing a product delivery' process?
- A. To ensure the business case is regularly reviewed
- B. To request authorization to start the next stage
- C. To assess whether the stage products have been approved
- D. To deliver the planned specialist products within tolerance
Answer: D
Explanation:
The objective of the 'Managing a Product Delivery' process in PRINCE2 is to ensure that the project's specialist products are delivered within the agreed tolerances. This process focuses on the acceptance, execution, and delivery of work packages, ensuring that each product meets the project's specifications and quality requirements. References: PRINCE2 7 Foundation Handbook and official training materials.
NEW QUESTION # 71
Which should be funded from a change budget?
- A. A fallback plan
- B. An agreed change to the scope of a project
- C. The Starting up a Project process
- D. A change to a plan, within allocated tolerances, due to poor estimating
Answer: B
Explanation:
Section: Volume A
NEW QUESTION # 72
Which is the purpose of the Change theme?
- A. To prevent change to baselined products
- B. To assess and control uncertainty
- C. To identify, assess and control any potential and approved changes to baselined products
- D. To establish mechanisms to monitor and compare actual achievements against those planned
Answer: C
Explanation:
Section: Volume A
NEW QUESTION # 73
Why is it crucial that the Project Product Description clearly defines acceptance methods?
- A. Enables Project Assurance to authorize quality activities
- B. Defines how all project products will be reviewed and approved
- C. Provides confirmation that all project products have met their quality criteria
- D. Defines how it will be proven that the completed project product meets the customer's expectations
Answer: D
NEW QUESTION # 74
Which is an objective of the 'starting up a project' process?
- A. To appoint the project management team
- B. To define the project quality management approach
- C. To approve the initiation stage
- D. To select the project mandate
Answer: C
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Starting_Up_a_Project#Purpose
NEW QUESTION # 75
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
- A. Controlling a Stage
- B. Directing a Project
- C. Managing a Stage Boundary
- D. Managing Product Delivery
Answer: A
NEW QUESTION # 76
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
- A. supplier
- B. product
- C. quality
- D. risk
Answer: A
NEW QUESTION # 77
Which is a purpose of a Product Description?
- A. Document the level of quality required of a product
- B. Record the quality checks completed for the End Stage Report
- C. Define reporting frequency
- D. Provide the cost tolerance available for individual products
Answer: A
NEW QUESTION # 78
......