The TOGAF framework is a widely recognized framework for enterprise architecture and is used by many organizations around the world. This certification exam is designed to test the knowledge and understanding of the TOGAF framework, including the core concepts, principles, and techniques. The exam covers topics such as the ADM (Architecture Development Method), architecture content framework, and architecture capability framework.


The Open Group OG0-092 exam, also known as the TOGAF 9 Part 2 exam, is a certification exam designed to assess the candidate's knowledge and understanding of the TOGAF framework. TOGAF stands for The Open Group Architecture Framework and is a globally recognized framework for enterprise architecture. The TOGAF 9 Part 2 exam is the second level of certification in the TOGAF 9 certification program and is intended for individuals who have already passed the TOGAF 9 Part 1 exam and want to further deepen their understanding of the framework.

 

NEW QUESTION # 22
Scenario: AGEX Inc.
Please read this scenario prior to answering the question
AGEX is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information.
The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, AGEX has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business. The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture.
After reviewing the available alternatives, and based on recommendations from the ERP vendor, AGEX has selected TOGAF 9 as the basis for its Enterprise Architecture program.
The CIO has endorsed this choice with the full support of top management.
Refer to the AGEX Inc. Scenario
You are serving as the Chief Architect.
As part of the process for establishing the Enterprise Architecture department, you have decided to create a set of principles to guide the activities.
You have been asked to recommend the best approach for this work.
Based on TOGAF 9, which of the following is the best answer?

  • A. You examine the mission statements for AGEX and each of its businesses, together with the corporate value statements. Based on that, you work with the Architecture Review Board to define the principles.When developing the principles you ensure that they actively promote the alignment of IT with the AGEX business strategies. You then run a series of reviews with all the relevant stakeholders, including senior management, ensuring their support.
  • B. You examine the mission statements for AGEX and each of its businesses, together with the corporate value statements. Based on that, you define a set of principles and review with the CIO.When developing the principles you ensure that they actively promote the alignment of IT with the business strategies and initiatives of AGEX. You then seek the endorsement of the CIO and senior management.
  • C. You define a set of principles that support the preferred best practices embodied in the Enterprise Architecture department charter. You publish the principles on the corporate intranet to ensure widespread acceptance and compliance.You then schedule regular periodic Compliance Assessments with individual business units to check that they have made satisfactory progress toward meeting the objectives and conditions embodied in the principles.
  • D. You gather information from credible industry sources in the commodities business. Based on that, you assess current trends and apply that to defining a set of principles that embody best practices.You select architecture principles that do not conflict with each other and that should be stable. You ensure that all the principles are realistic and avoid including principles that are obvious.

Answer: A


NEW QUESTION # 23

  • A. You recommend that the enterprise architects conduct a series of Compliance Assessments to ensure that
    the architecture is being implemented according to the contract. The Compliance Assessment should verify
    that the implementation team is using the proper development methodology. It should include deployment
    of monitoring tools and ensure that performance targets are being met. If they are not met, then changes to
    performance requirements should be identified and updated in the Implementation and Migration Plan.
  • B. You recommend that the enterprise architects assess how the plan impacts the other frameworks in use in
    the organization. Minimally, the plan should be coordinated with the business planning, portfolio/project
    management and operations management frameworks. They should then assign a business value to each
    project, taking into account available resources and priorities for the projects. Finally, they should generate
    the Implementation and Migration Plan.
  • C. You recommend that the enterprise architects place the Architecture Definition Document under
    configuration control. This will ensure that the architecture remains relevant and responsive to the needs of
    the enterprise. They should then produce an Implementation Governance Model to manage the lessons
    learned prior to finalizing the plan. You recommend that lessons learned be applied as changes to the
    architecture without review.
  • D. You recommend that the enterprise architects apply the Business Value Assessment Technique to prioritize
    the implementation projects and project increments. The assessment should focus on return on investment
    and performance evaluation criteria that can be used to monitor the progress of the architecture
    transformation. They should confirm the Transition Architecture phases using an Architecture Definition
    Increments Table to list tine projects. They should then document the lessons learned and generate the
    final Implementation and Migration Plan.
  • E. Based on all of these factors they have produced a risk
    assessment. They have also completed the Implementation and Migration Plan v0.1, the draft Architecture
    Roadmap, and the Capability Assessment deliverables.
    Because of the risks posed by the complexity of the current environment, it has been determined that a phased
    approach is needed to implement the target architectures. The overall implementation process is estimated to
    take several years.
    Refer to the Scenario
    You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.
    Based on TOGAF Standard Version 9.2, which of the following is the best answer?

Answer: C


NEW QUESTION # 24
Scenario:
Please read this scenario prior to answering the question
You are serving as the Lead Enterprise Architect at a major supplier in the automotive industry. The company is headquartered in Cleveland, Ohio with manufacturing plants across the United States, Brazil, Germany, Japan and South Korea. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
The company is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.
At a recent meeting, the Architecture Board approved a Request for Architecture Work sponsored by the Chief Engineer of Global Manufacturing Operations. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of diving their planning and production scheduling from a remote centralized system. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Scenario [Note: You should assume that the company has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.]
One of the earliest initiatives in the Enterprise Architecture program was the definition of a set of architecture principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution.
Based on TOGAF 9, which of the following is the best answer?

  • A. Common-use Applications, Control Technical Diversity, Ease of Use, Interoperability, Data is Shared, Data is Accessible, Data Security
  • B. Technology Independence, Data Trustee, Information Management is Everybody's Business, IT Responsibility, Responsive Change Management
  • C. Service-orientation, Responsive Change Management, Business Continuity, Data is Accessible, Data Security
  • D. Business Continuity, Common-use Applications, Maximize Benefit to the Enterprise, Data is Shared, Data is Accessible, Data Security

Answer: D


NEW QUESTION # 25
Scenario
Please read this scenario prior to answering the question
You have been assigned the role of Chief Enterprise Architect within a leading outsourcing services company.
The company has over 15,000 outsourcing professionals and works on some of the world's largest outsourcing projects. Outsourcing services include business processes, infrastructure, and service management. The company also provides business consulting services. Roughly half of its turnover comes from the private sector and half from the public sector.
With numerous service areas and a large number of diverse engagements in progress at any given time, overall engagement management within the company has become challenging. The company has recently had a number of high profile projects that have overrun on budget and under delivered, thereby damaging its reputation.
The company has an established an Enterprise Architecture program based on TOGAF 9, sponsored jointly by the Chief Executive Officer and Chief Information Officer. An Architecture Board has been formed comprised of IT staff executives and executives from the major service areas and consulting practice.
The Enterprise Architecture (EA) team has been working with the Strategic Planning team to create a strategic enterprise architecture to address these issues. The EA team has defined a framework and held workshops with key stakeholders to define a set of architecture principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains.
They have set out an ambitious vision of the future of the company over a five-year period. This will include three distinct transformations.
The CIO has made it clear that prior to the approval of the detailed implementation and Migration plan, the EA team will need to assess the risks associated with the proposed architecture. He has received concerns from some of the vice presidents across the company that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.
Refer to the Scenario
You have been asked to recommend an approach to satisfy these concerns.
Based on TOGAF, which of the following is the best answer?

  • A. The EA team should apply an interoperability analysis to evaluate any potential issues across the architecture. This should include the development of a matrix showing the interoperability requirements.
    Once all of the concerns have been resolved, the EA team should finalize the Architecture Roadmap and the Implementation and Migration Plan.
  • B. The EA team should evaluate the organization's readiness to undergo change. This will allow the risks associated with the transformations to be identified and mitigated for. It will also identify improvement actions to be worked into the Implementation and Migration Plan. The Business Value Assessment technique should then be used to determine the business value and associated risks for the transformation.
  • C. The EA team should bring together information about potential solutions from the appropriate sources.
    Once the target architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures. A value realization process should then be established to ensure that the concerns raised are addressed.
  • D. This can be used to understand the transformations that are required to achieve the proposed Target Architecture. The EA team should then assess the readiness of the organization to undergo change. Once the architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures.
  • E. Before preparing the detailed Implementation and Migration plan, the EA team should review and consolidate the gap analysis results from Phases B to

Answer: B


NEW QUESTION # 26
An international Insurance company has grown with little consideration for rationalization and consolidation.
There is no coordination between business unit and every one have managed its own applications. The CIO decided to establish an Enterprise Architecture program within the enterprise to enable the company to expand to other markets in the next two years. The company has not any Enterprise Architecture Capability in place and the he CIO has set up an Architecture Board and called its first meeting.
Refer to the scenario above
As Lead Architect you will establish a TOGAF 9 Enterprise Architecture program. Identify the best way to do this among the answers below.
Choose one of the following answers

  • A. You clarify the agreement on key business drivers and the scope of the enterprise architecture. You then clarify the requirements for architecture work. You define the architecture principles together with the help of the Architecture Board in order to lead the architecture work. You consider how to tailor TOGAF 9 for this enterprise.
  • B. You tailor TOGAF 9 with the help of the Architecture Board to integrate it with the legacy procedures established by the PMO. You also examine the relationship of TOGAF with other processes and frameworks for governance, systems development and operations management. You then define the footprint of the enterprise architecture.
  • C. As Lead Architect you create a Request for Architecture Work to allocate resources to work on the Architecture Vision. Based on the outcome of the Business Scenario technique you apply, you create the Common Systems Architecture to guide the choice of Solutions Building Blocks. These will be then used for integrating the systems across business units.
  • D. You conduct an Architecture Maturity Assessment. You then use the TOGAF ADM to state the requirements for the integration of a new company information management system into the organization. You then list a set of business goals together with the Architecture Board that will be a reference to the enterprise architecture program.

Answer: A


NEW QUESTION # 27
Scenario:
Please read this scenario prior to answering the Question
You are serving as the Lead Enterprise Architect at a major supplier in the automotive industry. The company is headquartered in Cleveland, Ohio with manufacturing plants across the United States, Brazil, Germany, Japan and South Korea. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
The company is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.
At a recent meeting, the Architecture Board approved a Request for Architecture Work sponsored by the Chief Engineer of Global Manufacturing Operations. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of diving their planning and production scheduling from a remote centralized system. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Scenario
During the initial meeting of the Common ERP Deployment architecture project team, a number of alternative recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team evaluates different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?

  • A. The team should use stakeholder analysis to understand who has concerns about the initiative. The team should then hold a series of interviews at each of the manufacturing plants using the business scenario technique. This will then enable them to identify and document the key high-level stakeholder requirements for the architecture.
  • B. The team should develop Baseline and Target Architectures for each of the manufacturing plants, ensuring that the views corresponding to selected viewpoints address key concerns of the stakeholders. A consolidated gap analysis between the architectures will then be used to validate the approach, and determine the capability increments needed to achieve the target state.
  • C. The team should exercise due diligence and carefully research vendor literature and conduct a series of briefings with vendors that are on the current approved supplier list. Based on the findings from the research, the team should define a preliminary Architecture Vision. The team should then use that model to build consensus among the key stakeholders.
  • D. The team should conduct a pilot project that will enable vendors on the short list to demonstrate potential solutions that will address the concerns of the stakeholders. Based on the findings of that pilot project, a complete set of retirements will be developed that will drive the evolution of the architecture.

Answer: A


NEW QUESTION # 28
Worldwide Mobile is a mobile telecommunications company formed through a series of mergers and acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and as result, customer service has been a major concern for the Chief Technology Officer.
Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average. The Corporate Marketing group has published some new finding about customer satisfaction. The customers appear to be switching to Air Light, a competitor, because of superior customer service. WorldwideMobile actually has better coverage in nearly all markets than Air Light, and good roaming agreement that keep rates low for business travellers. But customer satisfaction has remained low.
The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise-wide strategic plan. They have developed a business scenario which contains a good conceptual model of what needs to be done and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board.
The planning for the program has been underway for several months. WorldwideMobile has selected TOGAF 9 as the basis for its Enterprise Architecture.
The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation. The Executive Council has stated that the program should define specific initiatives to enable each regional business units to create an implementation of the Customer Service System. The implementation must meet the needs of the business unit and still provide the information needed to enable major improvements to the customer.
Refer to WorldwideMobile-2 Scenario
You are serving as the Lead Architect for the Performance and Integrity project of the Customer Service System program.
The project has been chartered to address the architecture(s) required to support the Customer Service System from an infrastructure perspective. At present time, the project team is conducting an architecture development project that is focused on the customer self service capability, which was defined as part of the earlier strategic planning activities. This capability will enable customers to access their accounts, pay bills, request account reviews, and provision services from any web-enabled device.
The project team has gathered information about the self-service capability, developed a business scenario, and used the results to define an Architecture Vision for achieving the capability.
You have been asked to recommend the course of action to complete the project.
Based on TOGAF 9, which of the following is best answer?

  • A. In the remaining architecture definition phases, the project team should map out the capability in the Technology domain. In the Phases E and F, the capability should be broken down into a set of Solution Building Blocks that define the Target Architecture. Where possible, the Solution Building Blocks should be drawn from the Architecture Repository. The completed Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will conduct Compliance Assessments to ensure that the Target Architecture is properly implemented.
  • B. The remaining architecture definition work should be focused on mapping out the technology and infrastructure capability in the Technology domain. In Phases E and F, the capability should be broken down into a set of Solution Building Blocks that will be implemented to realize the Target Architecture. The Solution Building Blocks will provide the basis for the completed Architecture Definition Document that will be submitted for approval. Upon approval, the implementation team will conduct Compliance Assessments to ensure that the self-service capability is compliant with the overall Enterprise Architecture.
  • C. In the remaining architecture definition phases, the project team should map out the capability across the Business, Information System and Technology domains. In the Phases E and F, the capability should be broken down into a set of increments that are sequenced into Transition Architectures that will lead to the realization of the Target Architecture. The resulting Solution Building Blocks will then provide the basis for the capability increment solutions. The complete Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will oversee the implementation process through monitoring Architecture Contracts and by conduction Compliance Assessments.
  • D. In the remaining architecture definition phases, the project team should map out the capability across the Business, Information System and Technology domains. In the Phases E and F, the capability should be broken down into a set of increments that defines the Target Architecture. The Solution Building Blocks will provide the basis for the capability increment solutions. The complete Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will oversee the implementation process through monitoring Architecture Contracts and by conducting Compliance Assessments.

Answer: C


NEW QUESTION # 29
Scenario
Please read this scenario prior to answering the question
You are serving as the Lead Architect for an insurance company, which has been formed through the merger of three previously independent companies. The company now consists of three divisions with the same names and division headquarters as their predecessors.
The lack of integration between the three divisions has increasingly caused problems in the handling of customer and financial information. The inability to share information has resulted in lost opportunities to
"leverage the synergies" that had been intended when the company was formed. At present, each division maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, and claims information, each division has different ways of defining these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a common web portal, contact center software suite, and document management system. Also the company has selected a single enterprise- wide customer relationship management (CRM) application to consolidate information from several applications that exist across the divisions. The application will be used by each of the divisions and accessed by third party partners through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the migration teams in each division. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.
TOGAF 9 has been selected as the core framework for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
Refer to the Scenario
In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board.
Based on TOGAF, which of the following is the best answer?

  • A. You start by clarifying the intent that the Board has for raising these concerns. This enables you to understand the implications of the concerns in terms of regulatory requirements and the potential impact on current business goals and objectives. You propose that a security architect or security architecture team be allocated to develop a comprehensive security architecture and that this be considered an additional domain architecture.
  • B. You identify and document the security and regulatory requirements for the application and the data being collected. You ensure that written policies are put in place to address the requirements, and that they are communicated across the organization, together with appropriate training for key employees.
    You identify constraints on the architecture and communicate those to the architecture team. You establish an agreement with the security architects defining their role within the ongoing architecture project.
  • C. You evaluate the implications of the concerns raised by the Corporate Board in terms of regulatory requirements and their impact on business goals and objectives. Based on this understanding, you then issue a Request for Architecture Work to commence an architecture development project to develop a solution that will address the concerns. You allocate a security architect to oversee the implementation of the new application that is being developed.
  • D. You evaluate the implications of the Board's concerns by examining the security and regulatory impacts on business goals, business drivers and objectives. Based on your understanding, you then update the current security policy to include an emphasis on the concerns. You define architecture principles to form constraints on the architecture work to be undertaken in the project. You then allocate a security architect to ensure that security considerations are included in the architecture planning for all domains.

Answer: B


NEW QUESTION # 30
Scenario:
Please read this scenario prior to answering the question
Your role is consultant to the Lead Architect within a company that manufactures a variety of small electromechanical devices. As part of a corporate-wide Lean Manufacturing initiative, the company has defined a strategic architecture to improve its ability to meet consumer demand and improve its ability to manage its supply chain. The strategic architecture called for the consolidation of multiple Enterprise Resource Planning (ERP) applications that have been operating independently in several of the divisions' production facilities. The goal is to replace the functionality of the existing applications with a new ERP product running as a single instance in the company's primary data center.
The company has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.
Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase

  • A. You would apply the Business Value Assessment Technique to prioritize the implementation projects and project increments. The assessment should focus on return on investment and performance evaluation criteria that can be used to monitor the progress of the architecture transformation. You would confirm the Transition Architecture phases using an Architecture Definition Increments Table to list the projects. You would then document the lessons learned and generate the final plan.
  • B. Based on all of these factors they have produced a risk assessment.
    Because of the risks posed by the complexity of the current environment, it has been determined that a phased approach is needed to implement the target architectures. The overall implementation process is estimated to take several years.
    Refer to the Scenario The Implementation and Migration Plan v0.l, the draft Architecture Roadmap, and the Capability Assessment deliverables are now complete. You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.
    Based on TOGAF 9, which of the following is the best answer?
  • C. You would assess how the plan impacts the other frameworks in use in the organization. Minimally, the plan should be coordinated with the business planning, portfolio/project management and operations management frameworks. You would then assign a business value to each project, taking into account available resources and priorities for the projects. Finally, you would generate the Implementation and Migration Plan.
  • D. You would conduct a series of Compliance Assessments to ensure that the implementation team is implementing the architecture according to the contract. The Compliance Assessment should verify that the implementation team is using the proper development methodology. It should include deployment of monitoring tools and ensure that performance targets are being met. If they are not met, then changes to performance requirements should be identified and updated in the Implementation and Migration Plan.
  • E. You would place the strategic Architecture Definition and Transition Architectures under configuration control as part of the ongoing architecture development cycle. This will ensure that the architecture remains relevant and responsive to the needs of the enterprise. You would then produce an Implementation Governance Model to manage the lessons learned prior to finalizing the plan. You recommend that lessons learned be accepted by the Architecture Board as changes to the architecture without review.

Answer: C


NEW QUESTION # 31
Scenario:
Please read this scenario prior to answering the Question
You have been assigned the role of Chief Enterprise Architect within a leading North American information technology services company. The company has a number of service portfolios including infrastructure, applications, business process outsourcing, accounting, and financial services.
With numerous practice areas and a multitude of diverse engagements underway at any given time, overall engagement management within the company has become challenging. The company does not want to risk its outstanding reputation or its international certifications and CMM ratings.
The Chief Executive Officer and Chief Information Officer have co-sponsored the creation of an Enterprise Architecture prog-am based on TOGAF 9. An Architecture Board has been formed comprised of IT staff executives and executives from the major practice areas.
The Enterprise Architecture team has been working with the Strategic Planning team to create a strategic enterprise architecture to address these issues. The team has defined a framework and held workshops with key stakeholders to define a set of architecture principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period. This includes a solution architecture including three distinct transformations.
The CIO has made it clear that prior to the approval of the detailed Implementation and Migration plan, the EA team will need to assess the risks associated with the proposed architecture. He has received concerns from some of the senior partners that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.
Refer to the Scenario
You have been asked to recommend an approach to satisfy these concerns.
Based on TOGAF 9, which of the following is the best answer?

  • A. You recommend that the EA team apply an interoperability analysis to evaluate any potential issues across the Solution Architecture. This should include the development of a matrix showing the interoperability retirements. Once all of the concerns have been resolved, the EA team should finalize the Architecture Roadmap and the Implementation and Migration Plan.
  • B. You recommend that the EA team should gather information about potential solutions from the appropriate sources. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures. A value realization process should then be established to ensure that the concerns raised are addressed.
  • C. You recommend that before preparing the detailed Implementation and Migration plan, the EA team should review and consolidate the gap analysis results from Phases B to D to understand the transformations that are required to achieve the proposed Target Architecture. The EA team should assess the readiness of the organization to undergo change. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures.
  • D. You recommend that the EA team apply the Business Transformation Readiness Assessment technique which will allow the risks associated with the transformations to be identified and mitigated for, it will also identify improvement actions to be worked into the Implementation and Migration Plan. A Business Value Assessment should be used to determine the business value and associated risks for the transformation.

Answer: D


NEW QUESTION # 32
Scenario: Eight Twelve
Eight Twelve has retail outlets throughout North America. An Enterprise Architecture practice already exists in Eight Twelve. Now the CEO and CIO decide that they want to use TOGAF9 to re-architect their Enterprise Architecture to cater to the changing strategies of Eight Twelve to better respond to the changes in the economic and technology environments.
Some of the key issues which need to be addressed in this re-architecting work are:
1.Since Eight Twelve's retail chain operate 24 hours a day and are expanding to South America and Europe, the retail chain business ecosystem should be able to withstand any unforeseen disruptions which might affect the chain's day to day operations. This is highly critical to ensure high levels of customer satisfaction and thus maintaining and enhancing Eight Twelve's revenue chain.
2.Dependency between the application components, which are the nerve centers to Eight Twelve's sophisticated range of services both external and internal, and the application platform and technology infrastructure should be minimal. This would facilitate scalability and ease of enhancement of the service offerings.
3.Eight Twelve uses the ARTS Data Model and the quality of data is of utmost importance for its operation.
4.Users of the Enterprise Information ecosystem should have an environment which is able to cater to their needs without any undue delays.
Which one of the following set of Architecture Principles do you feel is the most appropriate for these guidelines stated above for the TOGAF 9 architecting work which Eight Twelve is embarking on?

  • A. a) Maximize Benefit to the Enterprise b).Data is an Asset c) Data is Shared d) Requirements Based Change
  • B. a) Business Continuity b).Data Trustee c) Technology Independence d) Responsive Change Management
  • C. a) Maximize Benefit to the Enterprise b).Data Trustee c) Service Orientation d) Responsive Change Management
  • D. a) Business Continuity b).Data is an Asset c) Data is Shared d) Requirements Based Change

Answer: B


NEW QUESTION # 33
Scenario: Armstrong Defense Industries
Please read this scenario prior to answering the question
Armstrong Defense Industries is the prime contractor for the Dreadnought Unmanned Aircraft System program.
Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. Armstrong Defense is moving aggressively to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.
To achieve this goal, Armstrong Defense needs to define Baseline and Target Architectures. These architectures must address key stakeholders concerns such as:
1. What groups of people should be involved in procurement-related business processes?
2. What current applications do those groups use?
3. Which procurement-related business processes are supported by zero, one, or many existing applications?
4. What are the overall lifetimes of the Request for Proposal and Purchase Order business objects?
5. What non-procurement applications will need to be integrated with any new procurement applications?
6. What data will need to be shared?
At present, there are no particularly useful architectural assets related to this initiative. All assets need to be acquired and customized or created from scratch. The company prefers to implement existing package applications from systems vendors with little customization.
The architecture development project has just completed its Architecture Context iteration cycle and is about to begin the Architecture Definition iteration cycle.
Armstrong Defense is using TOGAF for its internal Enterprise Architecture activities. It uses an iterative approach for executing Architecture Development Method (ADM) projects.
Refer to the Armstrong Defense Industries Scenario
You are serving as the Lead Architect.
You have been asked to identify the most appropriate architecture viewpoints for this situation.
Based on TOGAF 9, which of the following is the best answer?

  • A. In the early iterations of the Architecture Definition: * Describe the Target Business Architecture with a Business Service/Function catalog and an Organization/Actor catalog* Describe the key business objects with Data Lifecycle diagrams* Describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix* Describe the Target Data Architecture with a System/Data matrixIn the later iterations of the Architecture Definition: * Describe the Baseline Business Architecture with a Business Service/Function catalog and a Business Interaction matrix* Describe the Baseline Application Architecture with an Application and User Location diagram and a System/Function matrix* Describe the Baseline Data Architecture with a Data Entity/Data Component catalog
  • B. In the early iterations of the Architecture Definition: * Describe the Baseline Business Architecture with an Organization/Actor catalog* Describe the Baseline Application Architecture with a System/Function matrix* Describe the Baseline Data Architecture using a Data Entity/Data Component catalogIn the later iterations of the Architecture Definition: * Describe the Target Business Architecture with en Organization/Actor catalog* Describe the Target Application Architecture using Application Communication diagrams end an Application Interaction matrix* Describe the Target Data Architecture with a System/Data matrix
  • C. In the early iterations of the Architecture Definition: * Describe the Target Business Architecture with a Business Service/Function catalog and a Business Interaction matrix* Describe the key business objects with Product Lifecycle diagrams* Describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix* Describe the Target Data Architecture with a Data Entity/Business Function matrix and a System/Data matrixIn the later iterations of the Architecture Definition: * Describe the Baseline Business Architecture with a Business Service/Function catalog and a Business Interaction matrix* Describe the Baseline Application Architecture with a System/Organization matrix and a System/Function matrix* Describe the Baseline Data Architecture with a Data Entity/Data Component catalog
  • D. In the early iterations of the Architecture Definition: * Describe the Baseline Business Architecture with a Baseline Business Process catalog* Describe the Baseline Application Architecture with a Technology Portfolio catalog* Describe the Baseline Data Architecture with a Data diagramIn the later iterations of the Architecture Definition: * Describe the Target Business Architecture with an Actor/Process/Data catalog* Describe the Target Application Architecture with a System/Technology matrix* Describe the Target Data Architecture with a Data Dissemination diagram

Answer: C


NEW QUESTION # 34
Chiamin Metals is a leading world-wide manufacturer for continuous casting and bottom pouring powders. In addition to mould powders, the company also produces cored wire for secondary metallurgy. Chiamin Metals offers a variety of products and uses a paper-based catalog to sponsor them. A new CIO has joint the enterprise and has set up a team of Enterprise Architects following the TOGAF 9 practice. The main challenge is now to offer to Chiamin Metals customers a centralized and reliable entry point for their request via the implementation of a global online portal. This will allow the management of new marketing activities and will enable the new Chiamin Metals' ecommerce service.
Refer to the scenario above
You are the Chief Architect and the CIO asked you to present an Architecture Vision to address the above business problem. Identify the best answer accordingly to the TOGAF 9.
Choose one of the following answers

  • A. You create a high-level view of the Target Architectures and then present them to the CIO.
  • B. As requested by the CIO you focus on the Architecture Vision documentation and apply the Business Scenarios technique to create a high-level view of the Baseline and Target Architectures also based on the stakeholder concerns, business capability requirements, scope, constraints, and principles.
  • C. As requested by the CIO you focus on the Architecture Vision and create a detailed view of the Baseline Architectures. This is done for Business, Data, Application and Technology domains and then presented to the CIO using the Architecture Definition Document.
  • D. You identify key stakeholders, their concerns, and define the key business requirements to be addressed in the architecture engagement and generate a Stakeholder Map. You Evaluate business capabilities and execute a Business Transformation Readiness Assessment. You apply the Business Scenarios technique to create a high-level view of the Baseline and Target Architectures also based on the stakeholder concerns, business capability requirements, scope, constraints, and principles.

Answer: D


NEW QUESTION # 35
Scenario:
Please read this scenario prior to answering the Question
You have been appointed as a consultant to the Lead Enterprise Architect of an international agricultural company that exports bulbs, flowers and seeds worldwide. The company has its headquarters in the Netherlands, and has sales and distribution centers in over 30 countries worldwide. Several of these centers include administrative, manufacturing, and research facilities.
To achieve full integration of their research capabilities with their development centers located in various climate zones, the company wants to develop strong self-directed teams in each location. It also wants to define new business models that are profitable while reducing their impact on the environment. The management team is deeply committed to ensuring that the company is a world leader in socially responsible seed development with a business strategy that focuses on profitability through environmentally friendly operating processes.
The international operations of the company are subject to legal and regulatory requirements for each country where they operate. The production of genetically modified seeds has governmental controls that are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was developing pest-resistant seeds.
The Governing Board is concerned about the risks posed in this complex global environment, and as a result has approved the expenditure of resources to establish an Enterprise Architecture program. They have requested to be informed about the status of projects that could impact regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given location. In addition, the research organization should be able to see that the architecture is appropriate for its needs.
TOGAF 9 has been mandated as the framework for the development and evolution of the Enterprise Architecture practice. The Preliminary Phase has been completed to establish the enterprise architecture capability for this project.
Refer to the Scenario
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Governing Board, legal staff, auditors and the research organization.
Based on TOGAF 9, which of the following is the best answer?

  • A. You recommend that each project architecture activity is developed using a consistent modeling approach that is uniform across all architecture projects. Each architecture should be defined based on this fixed set of models so that all concerned parties can examine the models to ensure that their issues and concerns have been addressed.
  • B. You recommend that a stakeholder map be developed. This will allow the architects to define groups of stakeholders that share common concerns. A set of views should be defined to address the concerns for each group of stakeholders. Architecture models should then be created for each view to address the stakeholders' concerns.
  • C. You recommend that a special report be created for those groups that have sufficient power and level of interest. This report should summarize the key features of the architecture with respect to the particular location. Each of these reports should reflect the stakeholders1 requirements.
  • D. You recommend that a set of models be created for each project architecture that can be used to ensure that the system will be compliant with the local regulations. Stakeholders should then view the models to verify that their concerns have been properly addressed.

Answer: B


NEW QUESTION # 36
Dante Manufacturing is a big supplier in the automotive industry, head quarter in London with main plants in New York, Milan, Toronto and Tokio. Each one of these plants has been operating its own Manufacturing Requirements Planning (MRP II) system, production scheduling and custom applications for production automation. Dante's objective is to minimize waste production improving production operations.
During an analysis of the process improvements was determined that a significant improvement on waste production could be achieved replacing the outdated MRPII system with a common Enterprise Resource Planning (ERP) located in London. Dante has well-developed governance and processes based on TOGAF 9. The Chief Engineer of Global Manufacturing operations is the business sponsor and issued a Request for Architectural Work. The architectural activity for the implementation of the new ERP platform is kicked off and the architectural vision is produced. Some concerns on the security, reliability, responsibility and time to manage change of driving the MRP II and production scheduling by a central system located in London are raised by the team of architects working on the project and by senior management of the various organizations. These last in particular, stressed the need to align the information management with the business.
Refer to the scenario above As Lead Architect you have been asked to update the IT architectural principles to address the concerns raised by the project stakeholders and the senior management.
According to TOGAF 9 (assuming the enterprise is using the example set of principles in TOGAF 9 Section
23.6), which of the following is the best answer?
Choose one of the following answers

  • A. Business Continuity, Service-Orientation, Data is Shared , Data is Accessible, Data is Secure, Responsive Change Management.
  • B. Requirements-Based Change, Ease-of-Use, Data is Normalized.
  • C. Common Use Applications, Data is Shared, Data is Accessible, Data is Secure, Interoperability, Control, Technology Independence.
  • D. Information Management is Everybody's business, IT Responsibility, Data Trustee, Technology Independence, Responsive Change Management.

Answer: D


NEW QUESTION # 37

  • A. You would apply the Business Value Assessment Technique to prioritize the implementation projects and project increments. The assessment should focus on return on investment and performance evaluation criteria that can be used to monitor the progress of the architecture transformation. You would confirm the Transition Architecture phases using an Architecture Definition Increments Table to list the projects. You would then document the lessons learned and generate the final plan.
  • B. You would conduct a series of Compliance Assessments to ensure that the implementation team is implementing the architecture according to the contract. The Compliance Assessment should verify that the implementation team is using the proper development methodology. It should include deployment of monitoring tools and ensure that performance targets are being met. If they are not met, then changes to performance requirements should be identified and updated in the Implementation and Migration Plan.
  • C. You would place the strategic Architecture Definition and Transition Architectures under configuration control as part of the ongoing architecture development cycle. This will ensure that the architecture remains relevant and responsive to the needs of the enterprise. You would then produce an Implementation Governance Model to manage the lessons learned prior to finalizing the plan. You recommend that lessons learned be accepted by the Architecture Board as changes to the architecture without review.
  • D. You would assess how the plan impacts the other frameworks in use in the organization. The plan should be coordinated with the business planning, portfolio/project management and operations management frameworks. You would then assign a business value to each project, considering available resources and priorities for the projects. Finally, you would generate the Implementation and Migration Plan.
  • E. Based on all of these factors they have produced a risk assessment.
    The implementation process is estimated to take four years. Because of the risks posed by the complexity of the current environment, a phased approach is needed to implement the target architectures. The implementation and Migration Plan v0 1, the draft Architecture Roadmap, and the Capability Assessment deliverables are now complete.
    Refer to the Scenario
    You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.
    Based on TOGAF standard, which of the following is the best answer?

Answer: D

Explanation:
Explanation


NEW QUESTION # 38
Please read this scenario prior to answering the question
You are serving as the Lead Architect for a chain of convenience stores, operating as a franchise, which has over 5000 retail outlets throughout the Asia-Pacific region. The stores operate 24 hours a day and 7 days a week and rely on point-of-sale technology to manage their inventory.
Stores place all orders on-line. The back-office systems collect real-time data to support ordering and product selection decisions including the tailoring of product assortment based on sales history, customer demographics as well as the next day's weather forecast. In many cases, several stores are located in neighboring areas. This strategy makes distribution to each store cheaper, as well as making multiple deliveries per day possible.
An Enterprise Architecture practice exists within the company, with the CEO and CIO as joint sponsors. They have decided to adopt TOGAF 9 within the practice and the first project is to restructure the Enterprise Architecture so that it can better accommodate the changing strategies within the company and also better respond to changes in economic and technical environments.
The CIO has stated that the following issues need to be addressed in the restructuring:
* The systems should be able to withstand any unforeseen disruptions which might affect day to day operations. This is highly critical for ensuring high levels of customer satisfaction and maintaining and growing revenue.
* Dependencies between the application components, the application platform, and technology infrastructure should be minimal and well defined. This will facilitate scalability and ease of enhancement of the service offerings.
* The company is adopting the ARTS Operational Data Model and Data Warehouse Model from the National Retail Federation. This will address past problems with data quality and inconsistent data.
* To remain competitive, new products and promotions must undergo market trials and if these are successful, deployed across the retail chain. Information systems must be able to manage changes and updates without undue delays.
Refer to the Scenario
[Note: You should assume that the company has adopted the example set of principles that are listed and defined in TOGAF, Section 23.6. You may need to refer to Chapter 23 of the reference text in order to answer this question.] You have been asked to identify the most relevant architecture principles for the current situation.
Based on TOGAF, which of the following is the best answer? [Note: The ordering of the principles listed in each answer is not significant.]

  • A. IT Responsibility, Data Security, Ease of Use, Requirements Based Change, Common Use Applications
  • B. Interoperability, Data is Accessible, Data is Shared, Requirements Based Change, Control Technical Diversity
  • C. Technology Independence, Business Continuity, Common Vocabulary and Data Definitions, Data Trustee, Responsive Change Management
  • D. Interoperability, Maximize Benefit to the Enterprise, Data Trustee, Data is an Asset, Responsive Change Management

Answer: D